16.01.2024 Wyndham Grand Residences Batumi Gonio. Riviera In the 1st half of block A the reinforcement of the roof slab is underway, in the 2nd half the dismantling of the roof slab formwork is underway. Excavation works are being carried out in the area of Block B. On the floors of block E, the laying of walls with ceramic block continues. - European Village

16.01.2024 Wyndham Grand Residences Batumi Gonio. Riviera In the 1st half of block A the reinforcement of the roof slab is underway, in the 2nd half the dismantling of the roof slab formwork is underway. Excavation works are being carried out in the area of Block B. On the floors of block E, the laying of walls with ceramic block continues.