16.07.2023 - Wyndham Grand Residences Batumi Gonio. Riviera - In Block A, dismantling of the column formwork has been completed. In Block E, ballast backfilling and waterproofing of the underground part of the building continues. - European Village

16.07.2023 – Wyndham Grand Residences Batumi Gonio. Riviera – In Block A, dismantling of the column formwork has been completed. In Block E, ballast backfilling and waterproofing of the underground part of the building continues.