16.09.2024 Wyndham Grand Residences Batumi Gonio. Villas Insulation of the floor slab in villas 6, 7, 8 and 9. Reinforcement of the floor slab in villas 6 and 7. Waterproofing of the foundation wall connection to the floor slab in villas 1-5 and 10. Installation of column formwork - villas 3 and 5. Fabrication of the reinforced frame of the columns in villa 4. Reinforcement of the foundation wall on villas 11 and 13. - European Village

16.09.2024 Wyndham Grand Residences Batumi Gonio. Villas Insulation of the floor slab in villas 6, 7, 8 and 9. Reinforcement of the floor slab in villas 6 and 7. Waterproofing of the foundation wall connection to the floor slab in villas 1-5 and 10. Installation of column formwork – villas 3 and 5. Fabrication of the reinforced frame of the columns in villa 4. Reinforcement of the foundation wall on villas 11 and 13.