17.04.2024 Wyndham Grand Residences Batumi Gonio. Riviera In Block A, the laying of walls with ceramic block continues. In Block B, reinforcement of the foundation slab and installation of the retaining wall formwork is underway. In the infrastructure building, waterproofing of the underground part of the foundation has been completed and backfilling of the soil is underway.