18.08.2024 Wyndham Grand Residences Batumi Gonio. Riviera Installation of staircase formwork continues at the site. Fireplaces are being installed in Block A. In Block B - laying of ceramic block walls and dismantling of the floor slab formwork. In block C - installation of the floor slab formwork on the second floor. And in block E - drilling of technological holes in the roof. - European Village

18.08.2024 Wyndham Grand Residences Batumi Gonio. Riviera Installation of staircase formwork continues at the site. Fireplaces are being installed in Block A. In Block B – laying of ceramic block walls and dismantling of the floor slab formwork. In block C – installation of the floor slab formwork on the second floor. And in block E – drilling of technological holes in the roof.