19.04.2024 Wyndham Grand Residences Batumi Gonio. Riviera Ceramic block wall masonry continues in Block A. Reinforcement of the foundation slab formwork has been completed and concreting has been carried out in Block B. Foundation slab formwork installation started in Block C. Backfilling of the infrastructure building is in progress.