21.09.2023 Wyndham Grand Residences Batumi Gonio. Riviera The reinforcement of the floor slab continues on the 1st floor of Block A. On the 3rd floor of block E the reinforcement of columns is in progress, and also in the block works on installation of staircase formwork are being carried out.