23.09.2024 Wyndham Grand Residences Batumi Gonio. Villas Villas 1, 4: backfill around the perimeter of the foundation. Villas 2, 10: insulation of the foundation. Villas 8-9: reinforcement of the floor slab, installation of formwork around the perimeter of the floor slab. Villa 12: reinforcement of the bottom of the foundation. Villas 15-16: geodetic surveying and installation of formwork for under-concrete foundation. Geodetic surveying of the formwork for the fence foundation is also in progress.