24.04.2024 Wyndham Grand Residences Batumi Gonio. Riviera On the 2nd floor of block A the ceramic block walls are being laid. In Block B, the installation of the vertical structure formwork continues. Reinforcement of the foundation slab is underway in Block C. Drainage excavation works continue on the territory.