24.08.2024 Wyndham Grand Residences Batumi Gonio. Aqua Pouring of reinforced concrete sides (frames) of balconies and their waterproofing, installation of gypsum cardboard framework of internal partitions, diamond drilling of engineering holes in floor slabs continue at the facility. On the 20th floor the laying of ceramic block walls is in progress. The concrete platform opposite the entrance to the site is being dismantled. Plastering of staircase sleeves with mineral wool and cement-sand mixture is in progress. - European Village

24.08.2024 Wyndham Grand Residences Batumi Gonio. Aqua Pouring of reinforced concrete sides (frames) of balconies and their waterproofing, installation of gypsum cardboard framework of internal partitions, diamond drilling of engineering holes in floor slabs continue at the facility. On the 20th floor the laying of ceramic block walls is in progress. The concrete platform opposite the entrance to the site is being dismantled. Plastering of staircase sleeves with mineral wool and cement-sand mixture is in progress.