30.08.2024 Elite Family Residence The installation of drywall rails on the walls of the bathrooms and the installation of metal railings is in progress. Finishing of the north, south and west facade, ventilation shafts on the roof, connection of units to the central water supply, installation of floor reducers and filters, draining and cleaning of fire tanks is in progress. On the first floor electrical works are in progress (wiring, continuity testing), and in the mockup - laying of floor tiles. - European Village

30.08.2024 Elite Family Residence The installation of drywall rails on the walls of the bathrooms and the installation of metal railings is in progress. Finishing of the north, south and west facade, ventilation shafts on the roof, connection of units to the central water supply, installation of floor reducers and filters, draining and cleaning of fire tanks is in progress. On the first floor electrical works are in progress (wiring, continuity testing), and in the mockup – laying of floor tiles.