31.08.2024 Elite Family Residence The installation of plasterboard rails on the walls of the bathrooms and the installation of metal railings is in progress. Finishing of the northern, southern and western facade, ventilation shafts on the roof, covering of external communications with aquapanels, preparation of the elevator shaft is in progress. On the first floor, electrical installation works are in progress (wiring, continuity testing), and in the mockup - floor tile laying. - European Village

31.08.2024 Elite Family Residence The installation of plasterboard rails on the walls of the bathrooms and the installation of metal railings is in progress. Finishing of the northern, southern and western facade, ventilation shafts on the roof, covering of external communications with aquapanels, preparation of the elevator shaft is in progress. On the first floor, electrical installation works are in progress (wiring, continuity testing), and in the mockup – floor tile laying.