Elite Family Residence
1. Finishing work.
— Installation of moldings.
— Laying porcelain stoneware.
— Facing travertine on the balconies.
— Painting works.
2. Facade works.
— Plastering of terrace parapets.
— Painting of balconies, 5th floor.
— Facing the facade with natural stone.
3. Installation of handrails on the terraces. 3.
4. Electrical installation works.