Elite Family Residence
1. Finishing works.
— Porcelain stoneware installation, the 1st- 5th floors.
— Installation of wall porcelain stoneware in the bathrooms, the 5th floor.
— Puttying the ceiling in the units, the 4th floor.
— Marble cladding of the staircases, penthouses.
— Installation of moldings, the 4th floor.
2. Facade works.
— Cladding the facade with natural stone.
— Installation of the railings of the central facade.
3. Installation of staircases railings.
4. Firefighting system installation.
5. Drywall frame installation.
Covering the engineering systems with drywall on the western facade, the 5th floor.