Wyndham Grand Batumi Gonio. Aqua 1. Facade works, the 18th – 19th floors. This includes the installation of facade elements on balconies. Facade is being winterized. The total area of the completed work is 130m2. 2. Glazing of stained glass windows, the 16th floor. Glass installation.- 23 units 3. Installation of drywall frames for internal partitions, on the 15th – 20th floors. Thus provides a strong and stable foundation for wall construction. 4. Cladding of decorative columns on the balconies on the 17th – 19th floors. 5. Water supply and sewer system installation. – Installation of stormwater drainage systems on the 10th floor. – Installation of sewage systems on the 18th – 19th floors. 6. Mockup construction on the 3rd and 13th floors. Finishing works in the mockup on the 3rd floor, and finishing sparkling of the ceiling in the mockup on the 13th floor. 7. Diamond core drilling for engineering openings on the 2nd -3rd floor Marking and drilling of precise openings for the installation of utilities in the future hotel – 18 engineering openings. 8. Material delivery. AAC blocks were unloaded.