Elite Family Residence1. Mock-up construction. This enables visualization and testing of design and materials. Finishing works are ongoing. 2. Cladding ceramic granite in the bathrooms, units on the 2nd – 3rd residential floors. 3. Facade works. The decorative elements are being installed to create a visually appealing and protected exterior for the building. 4. Marble cladding of staircases. This includes surface preparation, tile installation with precise alignment, and joint management according to the layout plan. 5. Installation of decorative mouldings and skirting boards on the 3rd floor. Additionally, work continues on the installation of a steel canopy, waterproofing of balconies on the 1st and 2nd floors, and terraces, as well as electrical installation, and cast-in construction in the backyard.