Elite Family Residence1. Mock-up construction. This enables visualization and testing of design and materials. Painting is underway. 2. Facade works. Installing decorative elements to enhance the building’s visual appeal and ensure exterior durability. 3. Cladding ceramic granite in the bathrooms, units on the 3rd – 4th residential floors. Tile grouting. 4. Marble cladding of staircases. This includes surface preparation, tile installation with precise alignment, and joint management according to the layout plan. 5. Installation of steel railings in the staircase vestibule. 6. Concrete works for the rear courtyard entrance group. The electrical installation, plumbing, and the installation of drywall frames are also in progress.