Monthly Construction Report Wyndham Grand Batumi Gonio. Family Club October 2025 In October 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project. Block A — During the installation of the roofing system, vapor barrier installation was completed, insulation with a slope was laid, and PVC membrane installation and insulation with a slope are underway. — Work is underway on the installation of the upper waterproofing coating for the balconies on the 2nd floor. . — Work is underway on the installation of porcelain stoneware on the balconies. — Plastering work is underway: reinforcement for the application of decorative plaster, plastering work on the outside of the balconies, plastering work on the facade of the block. — Facade work continues — installation of mineral wool, reinforcement and plastering, priming for the application of decorative plaster. — Work is underway on the installation of clinker tiles on the facade and the installation of stone window sills. — Decorative facade elements (cornices) have been ordered and are being delivered for subsequent installation. — Work is underway on the installation of clinker tiles on the facade. — Storm sewer risers have been installed from the roof, and storm sewer pipes have been delivered for installation. Block B — Work has been completed on the installation of the roofing system: installation of a vapor barrier layer, insulation layer, screed with slope, installation of water collection funnels, and installation of a PVC membrane. — Stained glass frames and double-glazed windows have been ordered and are being delivered. Installation of stained glass profiles is underway. — Work on installing the ceiling frame has been completed. Ceiling cladding is currently underway. — Work is underway on installing window slopes. — Work is underway on plastering terraces and interior walls, and plastering work has been completed on the facade under XPS. — Work is continuing on the installation of mineral wool on the 2nd and 3rd floors. — Work has been completed on the installation of metal storm sewer boxes on the 1st floor. - European Village

Monthly Construction Report
Wyndham Grand Batumi Gonio. Family Club
October 2025

In October 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project.
Block A
— During the installation of the roofing system, vapor barrier installation was completed, insulation with a slope was laid, and PVC membrane installation and insulation with a slope are underway.
— Work is underway on the installation of the upper waterproofing coating for the balconies on the 2nd floor. .
— Work is underway on the installation of porcelain stoneware on the balconies.
— Plastering work is underway: reinforcement for the application of decorative plaster, plastering work on the outside of the balconies, plastering work on the facade of the block.
— Facade work continues — installation of mineral wool, reinforcement and plastering, priming for the application of decorative plaster.
— Work is underway on the installation of clinker tiles on the facade and the installation of stone window sills.
— Decorative facade elements (cornices) have been ordered and are being delivered for subsequent installation.
— Work is underway on the installation of clinker tiles on the facade.
— Storm sewer risers have been installed from the roof, and storm sewer pipes have been delivered for installation.
Block B
— Work has been completed on the installation of the roofing system: installation of a vapor barrier layer, insulation layer, screed with slope, installation of water collection funnels, and installation of a PVC membrane.
— Stained glass frames and double-glazed windows have been ordered and are being delivered. Installation of stained glass profiles is underway.
— Work on installing the ceiling frame has been completed. Ceiling cladding is currently underway.
— Work is underway on installing window slopes.
— Work is underway on plastering terraces and interior walls, and plastering work has been completed on the facade under XPS.
— Work is continuing on the installation of mineral wool on the 2nd and 3rd floors.
— Work has been completed on the installation of metal storm sewer boxes on the 1st floor.