Monthly Construction Report
Wyndham Grand Batumi Gonio. Villas
November 2025
In November 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project.
— Monolithic work
Concreting of the internal staircases in the villas is being completed.
— Installation of side panels
Monolithic side panels for the installation of stained glass windows in 5 villas have been installed.
— Masonry work
The exterior walls of the third floor are being laid with ceramic blocks on all villas.
— Installation of fireplaces
Work has been completed on the installation of fireplaces on the first floor of 12 villas and the installation of chimneys on 13 villas.
— Stained glass glazing
Work is continuing on the installation of stained glass frames and
— Facade work
Facade work is underway to install mineral wool and insulate the facades of all villas. Work is being done to reinforce the mineral wool and apply primer. Work is also underway to install granite window sills.
— Plastering work
Plastering work is being done on the interior walls of the villas.