WWyndham Grand Batumi Gonio. AquaFacade works. – Plastering of facade walls, on the 2nd -20th floors. 2. Installation of drywall frames. – Installation of internal partitions, the 18th floor. 3. Mockup construction on the 3rd , 13th floors. – Finishing works. 4. Installation of utilities systems. – Hot and cold water supply risers are being installed, horizontal layout, the 6th – 7th, 20th floors. – Exhaust ventilation installation, the 14th-floor. – Wiring on the balconies, the 6th – 7th floors. – Stormwater drainage installation, mounting of hangers, the 18th , 20th floors. 5. Waterproofing of the balconies. On the 15th – 19th floors. 6. Fabrication and installation of steel arches Balconies on the 9th , 19th floors. 7. Construction of concrete ledges for stained glass installation. – Works are ongoing on the 10th floor. 8. Elevator shaft is being installed. – Laying of aerated silicate blocks, on the 4th floor. 9. Stained glass window installation, the 2nd – 20th floors. Ongoing installation of stained glass windows and glazing