Wyndham Grand Batumi Gonio. Aqua 1. Facade works. — Facade winterization, the 2nd, 4th, 5th, 7th,11th, 20th floors. — Plastering of facade walls, the 2nd — 20th floors. 2. Installation of utilities systems. — Wiring, the 12th — 17th floors. — Installation of water supply manifolds, the 3rd — 9th, 11th — 20th floors. 3. Fabrication and installation of steel arches Balconies on the 10th, 19th — 20th floors. 4. Ceramic block installation, the 10th, 20th floors. Construction with ceramic blocks. 5. Installation of suspended ceilings. Balconies on the 4th floor. 6. Drywall frame installation. On the 17th, 19th -20th floors. 7. Mockup installation. Wiring. 8. Floor screeding. On the balconies, the 4th floor. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Facade winterization, the 2nd, 4th, 5th, 7th,11th, 20th floors.
— Plastering of facade walls, the 2nd — 20th floors.

2. Installation of utilities systems.
— Wiring, the 12th — 17th floors.
— Installation of water supply manifolds, the 3rd — 9th, 11th — 20th floors.

3. Fabrication and installation of steel arches
Balconies on the 10th, 19th — 20th floors.

4. Ceramic block installation, the 10th, 20th floors.
Construction with ceramic blocks.

5. Installation of suspended ceilings.
Balconies on the 4th floor.

6. Drywall frame installation.
On the 17th, 19th -20th floors.

7. Mockup installation.
Wiring.

8. Floor screeding.
On the balconies, the 4th floor.