Wyndham Grand Batumi Gonio. Aqua
1. Facade works.
— Facade winterization, the 3rd, 5th, 7th, 14th floors.
— Plastering of facade walls, the 2nd- 20th floors.
2. Installation of utilities systems.
— Hot and cold water supply risers are being installed (horizontal layout), the 12th, 13th, 18th floors.
— Wiring on the balconies, the 18th floor.
— Installation of the exhaust ventilation, the 3rd -5th floors.
3. Fabrication and installation of steel arches
Balconies on the 20th floor.
4. Suspended ceiling installation.
On the balconies, the 3rd floor.
5. Waterproofing
Balconies of the 4th floor.
6. Drywall frame installation.
On the 19th — 18th floors.
7. Floor screeding.
On the balconies, the 3rd, 19th floors.
8. Installation of the elevator.
Installation of elevator shaft beams on the 17th — 20th floors.
9. Mockup construction on the 13th floors.
— Painting of the ceiling.
10. Diamond core drilling for engineering openings, the 15th -17th floors.
Marking and drilling of precise openings for the installation of utilities in the future hotel.