Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. Electrical installation work. 2. Installation of elevator shafts. Installation of elevator equipment. 3. Installation of plasterboard frames. Installation of ceiling frames. 4. Plastering work. Application of decorative plaster on balconies. 5. Masonry work, 10th floor. Laying ceramic blocks. 6. Drilling engineering holes. For further installation of engineering networks. 7. Infrastructure building Monolithic work, installation of formwork for the floor slab on the 3rd floor. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
Electrical installation work.

2. Installation of elevator shafts.
Installation of elevator equipment.

3. Installation of plasterboard frames.
Installation of ceiling frames.

4. Plastering work.
Application of decorative plaster on balconies.

5. Masonry work, 10th floor.
Laying ceramic blocks.

6. Drilling engineering holes.
For further installation of engineering networks.

7. Infrastructure building
Monolithic work, installation of formwork for the floor slab on the 3rd floor.