Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. Electrical installation work, installation of clips. 2. Installation of elevator shafts. Installation of elevator equipment. 3. Drilling of engineering holes. For further installation of engineering networks. Other construction work on the site is not being carried out today due to weather conditions. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
Electrical installation work, installation of clips.

2. Installation of elevator shafts.
Installation of elevator equipment.

3. Drilling of engineering holes.
For further installation of engineering networks.

Other construction work on the site is not being carried out today due to weather conditions.