Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
Electrical installation works, 13th floor.
2. Facade works.
Insulation of the facade on balconies, 4, 6, 11 floor.
3. Waterproofing works, 4–5 floors.
Work on the second layer of waterproofing on the balconies.
4. Works in the workshop.
Fabrication of embedded parts.
5. Welding works.
Installation of posts on the roof of the building.
6. Floor screed works.
On balconies, 17th floor.
7. Arrangement of suspended ceilings.
On the 8–9 floor.
8. Installation of gypsum plasterboard frame.
Closing of the frame, 20th floor.
9. Infrastructure building.
— Reinforcement of the floor slab.
— Dismantling of formwork