Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
Electrical installation works, 18th floor.
2. Facade works.
Insulation of the facade on balconies, 4, 11, 13 floors.
3. Waterproofing works, 4–5 floors.
Work on the second layer of waterproofing on the balconies.
4. Works in the workshop.
Fabrication of embedded parts.
5. Arrangement of columns and partitions of iron frame.
Works on 2–9, 11–20 floors.
6. Works on the arrangement of floor screed.
On the balconies, 16th floor.
7. Arrangement of suspended ceilings.
On the 8–9 floor.
8. Installation of gypsum plasterboard frame.
Closing of the frame,
9. Masonry works, roofing.
Ceramoblock masonry.
10. Closure of arches.
On the 20th floor.
11. Diamond drilling of engineering holes, on 2–9 floors.
For the device of communications.
12. Infrastructure building.
Reinforcement of vertical structures.