Wyndham Grand Batumi Gonio. Aqua. 1. Installation of engineering systems. — Electrical work, 13th and 14th floors. — Installation of fire extinguishing system, floors 6–20. — Sealing of ventilation openings. 2. Plastering works. Installation of decorative plaster on balconies. 3. Ceiling installation work, 14th-15th floors. Installation of ceiling frames on balconies, covering of frames. 4. Facade work. Plastering of the facade. 5. Infrastructure building. Concreting of floor slabs, 5th floor. - European Village

Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Electrical work, 13th and 14th floors.

— Installation of fire extinguishing system, floors 6–20.

— Sealing of ventilation openings.

2. Plastering works.

Installation of decorative plaster on balconies.

3. Ceiling installation work, 14th-15th floors.

Installation of ceiling frames on balconies, covering of frames.

4. Facade work.

Plastering of the facade.

5. Infrastructure building.

Concreting of floor slabs, 5th floor.