Wyndham Grand Batumi Gonio. Aqua. 1. Installation of engineering systems. — Electrical work, installation of clips, laying of electrical cables, 14th floor. — Installation of fire extinguishing system, 2nd-5th floors. 2. Plastering work. Installation of decorative plaster on balconies. 3. Installation of plasterboard frame. — Installation of frame for inter-unit partitions, 15th-16th floors. — Installation of insulation for inter-unit walls, 16th floor. 4. Finishing works, 9th floor. Laying tiles on balconies. 5. Installation of balconies for the panoramic elevator. Reinforcement of balconies. 6. Facade work. Plastering of the facade. 7. Infrastructure building. Reinforcement of floor slabs, 5th floor. - European Village

Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Electrical work, installation of clips, laying of electrical cables, 14th floor.

— Installation of fire extinguishing system, 2nd-5th floors.

2. Plastering work.

Installation of decorative plaster on balconies.

3. Installation of plasterboard frame.

— Installation of frame for inter-unit partitions, 15th-16th floors.

— Installation of insulation for inter-unit walls, 16th floor.

4. Finishing works, 9th floor.

Laying tiles on balconies.

5. Installation of balconies for the panoramic elevator.

Reinforcement of balconies.

6. Facade work.

Plastering of the facade.

7. Infrastructure building.

Reinforcement of floor slabs, 5th floor.