Wyndham Grand Batumi Gonio. Aqua. 1. Installation of engineering systems. — Electrical work, laying electrical cables, 7th floor. — Plumbing work, drainage installation, 17th floor. — Installation of air conditioning pipes. 2. Installation of plasterboard frame, 19th floor. Installation of inter-unit partition frames, insulation of internal partitions. 3. Finishing works, 9th and 19th floors. Tiling of balconies. 4. Plastering works. — Plastering of balconies. — Plastering of the facade. 5. Roof work. Tying up the roof trusses. 6. Installation of stained glass structures, 10th floor. Assembly of stained glass windows. 7. Installation of a panoramic elevator. Installation of formwork for the balconies of panoramic elevators. 8. Waterproofing work, 18th floor. Installation of coating waterproofing on balconies. 9. Infrastructure building. — Concreting of floor slabs, 7th floor. — Laying of ceramic blocks, 3rd floor. - European Village

Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Electrical work, laying electrical cables, 7th floor.

— Plumbing work, drainage installation, 17th floor.

— Installation of air conditioning pipes.

2. Installation of plasterboard frame, 19th floor.

Installation of inter-unit partition frames, insulation of internal partitions.

3. Finishing works, 9th and 19th floors.

Tiling of balconies.

4. Plastering works.

— Plastering of balconies.

— Plastering of the facade.

5. Roof work.

Tying up the roof trusses.

6. Installation of stained glass structures, 10th floor.

Assembly of stained glass windows.

7. Installation of a panoramic elevator.

Installation of formwork for the balconies of panoramic elevators.

8. Waterproofing work, 18th floor.

Installation of coating waterproofing on balconies.

9. Infrastructure building.

— Concreting of floor slabs, 7th floor.

— Laying of ceramic blocks, 3rd floor.