Wyndham Grand Batumi Gonio. Aqua. 1. Installation of engineering systems. — Electrical work, laying electrical cables, 7th floor. — Plumbing work, drainage installation, 18th floor. — Installation of air conditioning pipes. 2. Installation of plasterboard frame, 13th floor. Installation of frame for inter-unit partitions, insulation of internal partitions. 3. Finishing work, 8th and 18th floors. Laying tiles on balconies. 4. Plastering work. Plastering balconies. 7. Installation of a panoramic elevator. Installation of formwork for panoramic elevator balconies. 8. Waterproofing work, 18th floor. Application of coating waterproofing on balconies. 9. Infrastructure building. — Reinforcement of vertical structures, 8th floor. — Ceramic block masonry, 4th floor. - European Village

Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Electrical work, laying electrical cables, 7th floor.

— Plumbing work, drainage installation, 18th floor.

— Installation of air conditioning pipes.

2. Installation of plasterboard frame, 13th floor.

Installation of frame for inter-unit partitions, insulation of internal partitions.

3. Finishing work, 8th and 18th floors.

Laying tiles on balconies.

4. Plastering work.

Plastering balconies.

7. Installation of a panoramic elevator.

Installation of formwork for panoramic elevator balconies.

8. Waterproofing work, 18th floor.

Application of coating waterproofing on balconies.

9. Infrastructure building.

— Reinforcement of vertical structures, 8th floor.

— Ceramic block masonry, 4th floor.