Wyndham Grand Batumi Gonio. Aqua. 1. Installation of engineering systems. — Installation of a fire extinguishing system. — Plumbing work, 18th floor. — Installation of air conditioning pipes, 17th-18th floors. 2. Plastering work. Installation of decorative plaster on balconies. 3. Installation of plasterboard frame, 16th floor. Installation of inter-unit partition frames, insulation of inter-unit partitions. 4. Finishing works, 19th floor. Laying tiles on balconies. 5. Facade works. Plastering the facade. 6. Installation of a panoramic elevator. Installation and reinforcement of panoramic elevator slabs. 7. Infrastructure building. — Reinforcement of floor slabs, 6th floor. — Laying ceramic blocks, 2nd floor. - European Village

Wyndham Grand Batumi Gonio. Aqua.

1. Installation of engineering systems.

— Installation of a fire extinguishing system.

— Plumbing work, 18th floor.

— Installation of air conditioning pipes, 17th-18th floors.

2. Plastering work.

Installation of decorative plaster on balconies.

3. Installation of plasterboard frame, 16th floor.

Installation of inter-unit partition frames, insulation of inter-unit partitions.

4. Finishing works, 19th floor.

Laying tiles on balconies.

5. Facade works.

Plastering the facade.

6. Installation of a panoramic elevator.

Installation and reinforcement of panoramic elevator slabs.

7. Infrastructure building.

— Reinforcement of floor slabs, 6th floor.

— Laying ceramic blocks, 2nd floor.