Wyndham Grand Batumi Gonio. Aqua
1. Installation of engineering systems.
— Installation of electrical system, 20th floor.
— Installation of water supply system, 2, 9th floor.
2. Facade works.
— Plastering of the facade.
— Arrangement of facade insulation.
3. Diamond drilling of engineering holes.
For the device of engineering systems.
4. Plasterboard frame installation works.
5. Plastering works.
Plastering of balconies.
6. Finishing works, 2, 3 floor.
Laying tiles on the balconies.
7. Work on the floor screed.
On the 8th floor.
8. Mocap works, 3rd floor.
Finishing works.
9. Arrangement of ventilation shafts, roofing.
10. Infrastructure building.
Installation of floor slab formwork.