Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. — Installation of power supply system, 9th floor. — Installation of water supply system, 3–7 floors. 2. Facade works. — Facade insulation, 8–14 floors. — Plastering of the facade, 8–14 floors. 3. Floor screeding works. On the 12th floor. 4. finishing works, 1 floor. Laying ceramic tiles on the balconies. 5. Works on installation of gypsum plasterboard frame, 12, 16 floors. 6. Arrangement of mocap, 3 floor. Finishing works. 7. Works on the roof of the building. — Manufacturing and installation of props. — Drilling of engineering holes. 8. Works on the device of elevator shafts. Plastering works. 9. Infrastructure building. — Reinforcement of walls. — Installation of formwork. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of power supply system, 9th floor.
— Installation of water supply system, 3–7 floors.

2. Facade works.
— Facade insulation, 8–14 floors.
— Plastering of the facade, 8–14 floors.

3. Floor screeding works.
On the 12th floor.

4. finishing works, 1 floor.
Laying ceramic tiles on the balconies.

5. Works on installation of gypsum plasterboard frame, 12, 16 floors.

6. Arrangement of mocap, 3 floor.
Finishing works.

7. Works on the roof of the building.
— Manufacturing and installation of props.
— Drilling of engineering holes.

8. Works on the device of elevator shafts.
Plastering works.

9. Infrastructure building.
— Reinforcement of walls.
— Installation of formwork.