Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. — Installation of power supply system, 9th floor. — Installation of water supply system, 8–9 floors. 2. Facade works. — Facade insulation on balconies, 12–14 floors. — Plastering of the facade, 8, 15, 19 floors. 3. Floor screeding works. On the 12th floor. 4. Work on the device ceiling. On the 7th floor. 5. Finishing works, 2nd floor. Laying ceramic tiles on the balconies. 6. Plasterboard frame installation works, 18th floor. Closing of the frame. 7. Works on the device of elevator shafts. Plastering works. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of power supply system, 9th floor.
— Installation of water supply system, 8–9 floors.

2. Facade works.
— Facade insulation on balconies, 12–14 floors.
— Plastering of the facade, 8, 15, 19 floors.

3. Floor screeding works.
On the 12th floor.

4. Work on the device ceiling.
On the 7th floor.

5. Finishing works, 2nd floor.
Laying ceramic tiles on the balconies.

6. Plasterboard frame installation works, 18th floor.
Closing of the frame.

7. Works on the device of elevator shafts.
Plastering works.