Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. — Installation of storm water drainage risers, 19th-20th floor. — Electrical installation, 8th floor. — Plumbing installation, 11th to 12th floor. 2. Masonry works, 10th floor. Ceramoblock masonry. 3. Plastering works. Plastering of balconies. 4. Arrangement of elevator shafts. 5. Finishing works, 20th floor. Laying tiles on the balconies. 6. Waterproofing works. — Preparatory work for the application of waterproofing on the roof of the building. — Waterproofing of balconies, 20th floor. 7. Infrastructure building. Installation of floor slab formwork and reinforcement of the floor slab on the 1st floor. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of storm water drainage risers, 19th-20th floor.
— Electrical installation, 8th floor.
— Plumbing installation, 11th to 12th floor.

2. Masonry works, 10th floor.
Ceramoblock masonry.

3. Plastering works.
Plastering of balconies.

4. Arrangement of elevator shafts.

5. Finishing works, 20th floor.
Laying tiles on the balconies.

6. Waterproofing works.
— Preparatory work for the application of waterproofing on the roof of the building.
— Waterproofing of balconies, 20th floor.

7. Infrastructure building.
Installation of floor slab formwork and reinforcement of the floor slab on the 1st floor.