Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. — Installation of storm water drainage risers, 19th floor. — Electrical installation, 8th floor. — Plumbing work, installation of installations, 12th floor. 2. Facade works, 16–18 floors. Insulation of the facade. 3. Masonry works, 10th floor. Ceramoblock masonry. 4. Floor screed works. Works on the 15th floor. 5. Finishing works. Laying tiles 6. Waterproofing works, roofing. Preparatory work for the application of waterproofing on the roof of the building. 7. Infrastructure building. Installation of formwork for the floor slab of the 1st floor. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of storm water drainage risers, 19th floor.
— Electrical installation, 8th floor.
— Plumbing work, installation of installations, 12th floor.

2. Facade works, 16–18 floors.
Insulation of the facade.

3. Masonry works, 10th floor.
Ceramoblock masonry.

4. Floor screed works.
Works on the 15th floor.

5. Finishing works.
Laying tiles

6. Waterproofing works, roofing.
Preparatory work for the application of waterproofing on the roof of the building.

7. Infrastructure building.
Installation of formwork for the floor slab of the 1st floor.