Wyndham Grand Batumi Gonio. Aqua 1. Installation of engineering systems. — Plumbing works, on the roof. — Installation of storm water drainage. 2. Plastering works, 2–4, 9th floor. Plastering on balconies. 3. Facade works. Plastering of the facade. 4. Works on the roof of the building. Works on waterproofing. 5. Works on the floor screed. On the balconies of the 4th floor. 6. Works on the device of elevator shafts. 7. Works on the device gypsum plasterboard frame. Installation of partitions. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Plumbing works, on the roof.
— Installation of storm water drainage.

2. Plastering works, 2–4, 9th floor.
Plastering on balconies.

3. Facade works.
Plastering of the facade.

4. Works on the roof of the building.
Works on waterproofing.

5. Works on the floor screed.
On the balconies of the 4th floor.

6. Works on the device of elevator shafts.

7. Works on the device gypsum plasterboard frame.
Installation of partitions.