Wyndham Grand Batumi Gonio. Aqua 1. Installation of utilities systems. — Wiring, the 3rd, 16th, 19th floors. — Installation of water piping, the 17th floor. — Installation of exhaust ventilation system risers, the 8th- 9th floors. 2. Facade works. — Facade winterization, the 3rd, 5th floors. 3. Suspended ceiling installation. On the balconies, the 6th floor. 4. Insulation. On the 8th -15th floors. 5. Installation of elevator shafts. Laying of aerated blocks in the shafts. 6. Diamond drilling of the engineering openings, the roof. Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel. 7. Infrastructure building. Ongoing pit excavation. - European Village

Wyndham Grand Batumi Gonio. Aqua

1. Installation of utilities systems.
— Wiring, the 3rd, 16th, 19th floors.
— Installation of water piping, the 17th floor.
— Installation of exhaust ventilation system risers, the 8th- 9th floors.

2. Facade works.
— Facade winterization, the 3rd, 5th floors.

3. Suspended ceiling installation.
On the balconies, the 6th floor.

4. Insulation.
On the 8th -15th floors.

5. Installation of elevator shafts.
Laying of aerated blocks in the shafts.

6. Diamond drilling of the engineering openings, the roof.
Marking and drilling is carried out, which is necessary for the installation of engineering systems of the future hotel.

7. Infrastructure building.
Ongoing pit excavation.