Wyndham Grand Batumi Gonio. Aqua1. Diamond drilling for engineering openings, the 16th , 19th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2. Facade work, the 13th , 14th , 17th floors. This includes the installation of facade elements on balconies. Facade winterization. 3. Installation of stained glass, the 13th – 15th floors. Installation of 24 glass panes on the 13th floor. The construction of ledges for stained glass along with the stained glass installation. This ensures light permeability and improves thermal and sound insulation for hotel rooms. 4. Floor screeding on balconies, the 13th – 15th floors. 5. Installation of drywall frames for internal partitions, the 12th –14th floors. Thus provides a strong and stable foundation for wall construction, including framing and cladding. 6. Installation of decorative steel columns, floor 10th. It was installed 4 columns. 3 tops of the columns were welded. 7. Ceramic block Installation, the 20th floor. Installation of ceramic blocks in accordance with the technology. Ensuring the flatness and verticality of the walls. Checking all joints and corners for compliance with design specifications. 8. Installation of plumbing and sewage systems. The installation of the sewerage system on the 11th – 16th floors continues. The installation of the stormwater drainage system on the 12th – 18th floors is underway.