Wyndham Grand Batumi Gonio. Aqua1. Diamond drilling for engineering openings, the 4th – 6th , 18th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2. Facade work, the 14th – 15th floors. This includes the installation of facade elements on balconies. Facade winterization. 3. Installation of stained glass, the 13th – 15th floors. The construction of ledges for stained glass along with the stained glass installation. This ensures light permeability and improves thermal and sound insulation for hotel rooms. 4. Installation of drywall frames for internal partitions. Thus provides a strong and stable foundation for wall construction. Enclosing niches on the 9th, 11th, and 12th floors, and installing profiles on the 3rd to 9th floors are ongoing. 5. Installation of decorative steel columns, floor 10th. 6. Installation of plumbing and sewage systems. The installation of the sewerage system and stormwater drainage system. 7. Material delivery. The mineral wool was delivered for façade winterization.