Wyndham Grand Batumi Gonio. Aqua1. Diamond drilling for engineering openings, the 4th – 6th, 18th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2. Facade works, the 14th floor. This includes the installation of facade elements on balconies. Facade is being winterized. 3. Installation of stained glass, the 14th – 15th floors. The stained glass is being installed on the 14th – 15th floors, and the construction of ledges for stained glass is in progress on the 20th floor. This ensures light permeability and improves thermal and sound insulation for hotel rooms. 4. Installation of drywall frames for internal partitions. Thus provides a strong and stable foundation for wall construction. Enclosing niches on the 6th -9th floors is in progress. 5. Installation of decorative steel columns, floor 10th. 6. Installation of plumbing and sewage systems. The installation of the sewerage system and stormwater drainage system. 7. Mockup installation. Engineering and finishing works.