Wyndham Grand Batumi Gonio. Aqua1. Diamond drilling for engineering openings, the 9th floor. Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained glass. The construction of ledges for stained glass on the 13th -14th floors along with the stained glass installation. This ensures light permeability and improves thermal and sound insulation for hotel rooms. 3. Facade work, the 12th -14th floors. This includes the installation of facade elements on balconies. 4. Ceramic block Installation, 20th floor. Installation of ceramic blocks in accordance with the technology, ensuring wall alignment and verticality. Checking all joints and angles for compliance with the design specifications. 5. Mock-up construction, 12th floor. This allows for the visualization and verification of the design and materials for the hotel room. The finish puttying. 6. Installation of plumbing and sewage systems. Installation of the sewerage system and sealing of sewer risers on the 8th – 13th floors. Installation of the stormwater drainage system on the 7th – 9th floors. 7. Installation of decorative steel columns, floors 18th -20th. Anchoring the upper sections of the columns The following activities are also in progress: the installation of drywall frames for interior partitions and the dust removal of elevator shafts.