Wyndham Grand Batumi Gonio. Aqua1. Facade works. – Facade plastering. – Façade winterization, on the 7th -13th floors. 2. Installation of drywall frames. – Installation of internal partitions, the 6th – 9th , 11th floors. – Cladding of ledges, the 11th –13th floors. 3. Mockup construction on the 13th floor. Mockup installation is in progress. 4. Diamond core drilling for engineering openings on the 16th, 17th floors. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems. – Hot and cold water supply risers are being installed, the 11th -14th floors. – Cladding of the stormwater drainage duct, the 2nd -9th floors. – Exhaust ventilation installation, the 11th – 12th floors. 6. Waterproofing of the balconies. On the 11th floor. 7. Fabrication and installation of steel arches Balconies on the 9th -19th floors. 8. Construction of concrete ledges for stained glass installation. – Cast-in and reinforcement of the ledges for stained glass, on the 4th , 19th floors. – Concreting of the ledges, the 10th floor. 9. Floor screeding, the 2nd , 9th floors. The floor screeding is being installed. 10. Elevator shafts are being installed, the 3rd , 4th floors. – Masonry works.