Wyndham Grand Batumi Gonio. Aqua1. Facade works. – Facade plastering, the 2nd – 20th floors. – Facade works, on the 11th -20th floors. 2. Installation of drywall frames. – Installation of internal partitions, the 11th – 14th floors. – Installation of the columns on the drywalls, the 2nd – 9th, and 11th -20th floors. – Cladding of niches, the 7th -9th floors 3. Mockup construction on the 3rd , 13th floors. – Finishing works. – Tiling on the balconies. 4. Diamond core drilling for engineering openings on the15th floor, the roof. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems. – Hot and cold water supply risers are being installed, the7th , 8th , 11th floors. – Exhaust ventilation installation, the 12th- 14th floors. – Wiring on the balconies, 2nd – 3rd floors. – Stormwater drainage installation, mounting of hangers, the 14th -16th floors. 6. Waterproofing of the balconies. On the 19th floor. 7. Fabrication and installation of steel arches Balconies on the 9th , 19th floors. 8. Construction of concrete ledges for stained glass installation. – Works are ongoing on the 10th floor. 9. Floor screeding. – The floor screeding on the balconies, the 15th floors. – Screeding on the floors, the 18th floor. 10. Elevator shafts are being installed. – Laying of aerated silicate blocks, on the 5th- 6th floors. 11. Installation of stained glass windows on the 2nd -20th floors. The ongoing works to install stained glass windows. 12. Cladding of steel columns with fiber cement boards, the 2nd – 19th floors. 13. Installation of suspended ceiling on the balconies, the 2nd – 19th , 11th – 20th floors.