Wyndham Grand Batumi Gonio. Aqua1. Facade works. – Facade plastering, the 2nd -20th floors. – Facade works, on the 11th -20th floors. 2. Installation of drywall frames. – Installation of internal partitions, the 11th – 164h floors. – Drywall installation at the bottom part of the frame for floor screeding, the 14th -16th floors. – Installation of the columns on the drywalls, the 2nd – 9th, and 11th -20th floors. – Cladding of niches, the 7th -9th floors 3. Mockup construction on the 3rd , 13th floors. Finishing works. 4. Diamond core drilling for engineering openings on the15th floor, the roof. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems. – Hot and cold water supply risers are being installed, the 11th floor. – Cladding of the stormwater drainage duct, the 2nd -9th floors. – Exhaust ventilation installation, the 11th -12th floors. 6. Waterproofing of the balconies. On the 15th floor. 7. Fabrication and installation of steel arches Balconies on the 9th floor. 8. Construction of concrete ledges for stained glass installation. – Works are ongoing on the 10th floor. 9. Floor screeding. – The floor screeding on the balconies, the 13th -14th floors. – Screeding on the floors. 10. Elevator shafts are being installed. – Laying of aerated silicate blocks, on the 4th -5th floors. – Beams are being concreted for the walls of the elevator hall. – The walls of elevator shafts are being prepared. 11. Installation of stained glass windows on the 2nd -20th floors. The stained glass windows are being installed. 12. Cladding of steel columns with fiber cement boards, the 11th – 19th floors.