Wyndham Grand Batumi Gonio. Aqua1. Facade works. – Facade works, on the 11th -20th floors. 2. Installation of drywall frames. – Installation of internal partitions, the 18th floor. 3. Mockup construction on the 3rd , 13th floors. – Finishing works. – Tiling on the balconies. 4. Diamond core drilling for engineering openings on the15th floor. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems. – Hot and cold water supply risers are being installed, the 6th – 7th floors. – Exhaust ventilation installation, the 13th-floor. – Wiring on the balconies, the 4th floor. – Stormwater drainage installation, mounting of hangers, the 17th -18th floors. 6. Waterproofing of the balconies. On the 15th – 19th floors. 7. Fabrication and installation of steel arches Balconies on the 9th , 19th floors. 8. Construction of concrete ledges for stained glass installation. – Works are ongoing on the 10th floor. 9. Floor screeding. – The floor screeding on the balconies, the 15th floors. – Screeding on the floors, the 18th floor. 10. Elevator shaft is being installed. – Laying of aerated silicate blocks, on the 5th- 6th floors. 11. Installation of stained glass windows on the 2nd -20th floors. The ongoing works to install stained glass windows.