Wyndham Grand Batumi Gonio. Aqua
1. Facade works.
— Plastering of facade walls, on the 2nd -20th floors.
— Facade installation, the 14th — 20th floors.
2. Installation of utilities systems.
— Hot and cold water supply risers are being installed, horizontal layout, the 3rd — 4th floors.
— Exhaust ventilation installation, the
— Installation of risers.
— Wiring on the balconies, the 11th — 13th floors.
3. Fabrication and installation of steel arches
Balconies on the 9th floor.
4. Stained glass window installation, the 2nd — 20th floors.
Ongoing installation of stained glass windows and glazing.
5. Mockup construction on the 13th floor.
— Facade installation.
6. Waterproofing
On the balconies.
7. Diamond core drilling for engineering openings14th floor.
Marking and drilling of precise openings for the installation of utilities in the future hotel.
8. Elevator shafts are being installed.
— Walls are being prepared in the elevator shafts.
— Laying of aerated silicate blocks, on the 3rd — 4th floors.