Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Plastering of facade walls, on the 2nd — 20th floors.
— Facade winterization, the 3rd — 7th, 12th -13th floors.

2. Installation of utilities systems.
— Hot and cold water supply risers are being installed (horizontal layout), the 3rd, 6th, 11th- 12th floors.
— Installation of exhaust ventilation, the 18th floor.
— Wiring on the balconies, the 20th floor.

3. Fabrication and installation of steel arches
Balconies on the 19th floor.

4. Floor screeding
By floors, the 6th floor.

5. Mockup construction on the 13th floor.
— Ceiling sanding.

6. Waterproofing
Balconies of the 8th floor.

7. Diamond core drilling for engineering openings, the 8th -9th floors.
Marking and drilling of precise openings for the installation of utilities in the future hotel.

8. Drywall frame installation.
— Installation of partitions, the 3rd floor.
— Installation of columns across the drywall, the7th, 20th floor.

9. Elevator shafts installation
— Laying of gas silicate blocks, the 7th — 8th floors.

10. Suspending ceiling installation.
On the balconies, the 3rd floor.