Wyndham Grand Batumi Gonio. Aqua

1. Facade works.
— Plastering of facade walls, on the 2nd — 20th floors.
— Facade winterization, the 3rd,7th, 12th -13th floors.

2. Installation of utilities systems.
— Hot and cold water supply risers are being installed (horizontal layout), the 5th, 7th, 11th- 12th,15th — 17th floors.
— Installation of exhaust ventilation, the 17th floor.
— Wiring on the balconies, the 20th floor.

3. Fabrication and installation of steel arches
Balconies on the 9th, 19th floors.

4. Floor screeding
By floors, the 4th — 7th floors.

5. Mockup construction on the 13th floor.
— Finishing works

6. Waterproofing
Balconies of the 5th — 18th floors.

7. Diamond core drilling for engineering openings, the 12th floor.
Marking and drilling of precise openings for the installation of utilities in the future hotel.

8. Drywall frame installation.
— Installation of partitions, the 16th — 20th floors.

9. Elevator shafts installation
— Laying of gas silicate blocks, the 7th — 8th floors.