Wyndham Grand Batumi Gonio. Aqua1. Facade works, the 12th – 13th floors. This includes the installation of facade elements on balconies. The facade is being winterized. 2. Installation of drywall frames, the 14th -15th, 18th – 19th floors. 3. Mockup construction on the 3rd, 13th floors. – Painting is ongoing on the 3rd floor. – Tiling on the balconies of the 13th floor. 4. Diamond core drilling for engineering openings on the 4th, 17th – 18th floors. Marking and drilling of precise openings for the installation of utilities in the future hotel. 5. Installation of utilities systems – Horizontal water supply piping across units, the 20th floor – Stormwater drainage, steel bracket installation, the 8th – 5th floors. – Hot and cold water risers are being installed, the 19th – 20th floors. 6. Waterproofing balconies on the 4th – 5th floors. 7. Pouring for steel railing posts on balconies, the 6th – 7th floors. 8. Fabrication and installation of steel arches On balconies of the 9th floor.